Desert Company purchased land to be used as a factory site for $1,250,000. Desert paid $120,000 to tear down two buildings on th
e land. Salvage was sold for $8,000. Legal fees of $5,220 were paid for title investigation and making the land purchase. Architect’s fees were $46,800. Title insurance cost $3,600 and liability insurance during construction cost $3,900. Excavation cost $15,660. The contractor was paid $4,200,000. Landscaping cost $9,600. Interest costs during construction were $255,000. The cost of the building that should be recorded by Wilson Co. is:_________
The Cost of an asset include Purchase Cost and other costs directly incurred to put the asset in the location and condition intended for use by management.
Calculation of Cost of the Building :
Architect’s fees $46,800
Insurance $3,600
liability insurance $3,900
Excavation $15,660
Contractor $4,200,000
Total $4,269,950
Therefore,
The cost of the building that should be recorded by Wilson Co. is $4,269,950
A good relationship between a leader and his/her employees will boost up the confidence among them. Moreover, the communication gap which exist otherwise, will no longer be found.
Employees would be comfortable in giving feedback and would not lie for the sake of job, and they would even be able to share their problems with supervisors with less awkwardness.
Leaders support their employees and in turn they get genuine results from them, and this is scene in most of the cases.