Answer:
True
Explanation:
Critical-Chain
This was introduced or originated by Eli Goldratt in 1997. Its aim is to challenges conventional project management approaches and absolute dependence on TOC principles. The idea of what to change or eliminated is the largely rooted behaviors that is common with the traditional project management practices. It is very multitasking anf it is the longest string of reliance that occur on the project.
Critical- Chain Approach
This approach simply covers project network as it ca be limited by both resource and technical reliance/dependencies. each type of limitations can create task reliance.
The Summary of Critical Chain Approach
1.) use Aggressive but Possible Times (ABPT) for task durations
2.) identify the critical chain by accounting for resource dependencies
3.) use buffer management to track project progress etc.
Weight data is your answer
Answer:
I would say C
Explanation:
I motivate myself for college, by trying to get scholarships myself
Answer:
the sum of all prices that the individual buyers are willing and able to pay for each possible quantity of the good.
Explanation:
Market demand refers to the sum of the individual demand for a commodity from all buyers in a given market.
A market demand curve is therefore a graph that shows the the sum of the individual demand for a commodity from all buyers in the market.
Therefore, the correction option is "the sum of all prices that the individual buyers are willing and able to pay for each possible quantity of the good".
Note that the market demand curve is a downward sloping curve due to the fact that there is a negative relationship between price and quantity demanded. That is, as price increases, the quantity demanded decreases. On the other hand, as price decreases, the quantity demanded increases.
Also note that an example of a market demand curve is given in the attached graph. From the graph, it can be seen that when price is
, quantity demanded is
. But when price falls to
, quantity demanded increased to
. This shows the negative relationship between price and quantity demanded as explained above.
Answer:
Estimated manufacturing overhead rate= $10 per direct labor hour
Explanation:
Giving the following information:
Estimated manufacturing overhead= $2,886,000
Estimated direct labor hours= 288,600
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 2,886,000/288,600= $10 per direct labor hour