Explanation:
5800 is interest,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,, ,,,
Answer:
Machine B has a higher NPV therefore should be produced
The machine with the higher Net Present Value (NPV) should be produced .
NPV of Machine A
PV of cash flow
PV of annual profit = A × (1- (1+r)^*(-n)/r
A- 92,000, n- 11, r- 12%
PV = 92,000 × (1- (1.12^(-11)/0.12 = 546268.32
PV of salvage value = 13,000× 1.12^(-11)= 3737.189
NPV = 546268.320 + 3737.189 -250,000 = $300,005.50
NPV of Machine B
A- 103,00, n- 19, r- 12%
PV = 103,000 × (1- (1.12^(-19)/0.12= 758675.0165
Pv of salvage value = 26000× 1.12^(-19)= 3018.776199
NPV =758675.0165 + 3018.77 -460,000 = $301,693.79
Machine B has a higher NPV , therefore should be produced.
Howdy y'all!!
the answer is
general partnership
thank you
best regards
OFFICIALLYSAVAGE2003
Answer: $480
Given that,
Scrap value of metal = $480
press is six years old, Original cost = $174,000
Current book value = $3,570
Since, we know that the realizable value of the printing press is only $ 480, so tattle teller should assign the same as the initial cost of the new project.
Hence, $480 will be the initial cost of press for the new project.
Part 1. B Reject
Part 2. Division H's project should be rejected, because its return is less than the risk-based cost of capital for the division.
Division H's project should be rejected, because its return is less than the risk-based cost of capital for the division.