Answer: B. $40,000, $960,000
Explanation:
The long term obligation will be 80% of the collateral value which will be:
= 80% × $1.2 million
= 0.8 × $1,200,000
= $960,000.
Therefore, the short term obligation will be:
= $1,000,000 - $960,000
= $40,000
Answer:
$2.50
Explanation:
Calculation for the estimation of variable cost per unit
Units Total cost
High method 15,000×$5 per units =$75,000
(5,000*3)=15,000
Low method 5,000*$10 per units=$50,000
Difference 10,000 $25,000
Variable cost per unit =$25,000/10,000
Variable cost per unit=$2.50
Note: Based on the information given we were told that production tripled to its highest level which means the high method units will be 15,000 units (5,000 units*3)
Therefore Fremont would estimate its variable cost per unit as: $2.50
Answer:
$800,000
Explanation:
Given that;
Sales revenue = $800,000
Cash collected = $645,000
Remaining amount cash collected in January = $155,000
And the delivery of goods is $11,100
Here, since the service revenue earned is $800,000 and same amount would be reported under the income statement, other items given would be ignored.
It therefore means that the sum of $800,000 should be the 2019 income statement report for service revenue.
Answer:
Finish phase of the project life cycle.
Explanation:
The finish phase (or termination, or completion phase) of a project life cycle is basically when the project is completed and it is being delivered to the customer. Depending on the project, paperwork and documents are handed out to the customer, contracts with workers and suppliers are terminated. Everyone involved with the project must be notified about its completion and all obligations are paid for.
Answer: D
Explanation:
Use the Mutlilevel List Icon