Answer:
D. market segmentation
Explanation:
Market segmentation is the process by which consumers are grouped on the basis of some shared characteristics. The grouping helps businesses develop strategies that will effectively meet the needs of the target customer segment.
Consumers share common characteristics like common needs, interest and location. They are expected to respond in a similar way to marketing effort.
When real estate firms identify submarkets, such as property types or particular sections of a city, in which they can specialize and concentrate their transaction activity they are involved in market segmentation.
Answer:
overhead Lowden Company should record in the current period is $109200
Explanation:
given data
overhead rate = 156%
direct labor cost = $71,000
direct materials cost = $70,000
to find out
amount of overhead Lowden Company should record in the current period
solution
we find here first basis of allocation of overhead that is equal to direct material cost
and direct material cost is $70000
so
overhead in the current period will be
overhead in the current period = 70000 x 156%
overhead in the current period = 109200
so overhead Lowden Company should record in the current period is $109200
Answer:
c. Allow a time period for socializing to support the development of a team identity.
Explanation:
Project meetings are intended to solve problems and effectively communicate among team members. A successful project meeting is characterized by good preparation, establishing appropriate start and end time to cover the agenda, having a defined agenda to provide direction to the meeting and documenting all the decisions to ensure follow-ups. Therefore, socializing to support the develop the development of a team identity is not one of the factors since this could lead to a groupthink and discourage creativity.
Complete/Correct Question:
As a technical project manager you have decided to propose implementing a prototyping methodology for a small web-based design project. What is the first step you will follow in this project?
A. Use the existing prototype.
B. Identify user requirements.
C. Conduct a feasibility study.
D, Identify different solutions.
E, Develop an initial prototype.
Answer:
B, identify user requirements
Explanation:
When prototyping a methodology, it is very important that the project manager identifies or asks for the requirements of the client to ensure that the design doesn't come off as meaningless.
Cheers.