Answer:
Normal spoilage rate = 1.6978% (Approx)
Explanation:
Given:
Total unit produce = 11,900 units
Normal spoil unit = 200 units
Abnormal spoil unit = 120 units
Total normal unit produce = 11,900 - 120 = 11,780
Computation of normal spoilage rate:
Normal spoilage rate = Normal spoil unit / Total normal unit produce
Normal spoilage rate = 200 / 11,780
Normal spoilage rate = 0.0169779287
Normal spoilage rate = 1.6978% (Approx)
Answer: $54,000
Explanation:
Referring to the data regarding store operation given above, difference between cash receipt and cash disbursement for December could be calculated as follows;
December Cash receipt = (340,000*20%+320,000*80%) = 324,000
November Purchases = (340,000 × 75%)+(320,000 × 75% × 60%) - 153,000 = 246,000
December Cash payment = 246,000 +240,000 = 270,000
The difference between cash receipts and cash disbursement for December = 324,000 - 270,000 = 54,000
Answer:
Option (B) is correct.
Explanation:
Sales forecast = 2079 units
Ending Inventory to be maintained:
= 10% of forecast sales
= 10% (2079 units)
= 208 units
Production:
= Sales + Ending Inventory - Beginning Inventory
= 2079 units + 208 units - Nil
= 2,287 units
Taking current inventory into account, Dell's Production of 2,287 units After Adjustment have to be in order to have a 10% reserve of units available for sale.
Answer:
D. Only customers receive a financial institution privacy notice automatically
Explanation:
Let us take an illustration of all the points, primarily A is inaccurate because simply customers acquire a financial institution's privacy note directly. B and C are unreliable because, depending on the bank's privacy practices, both consumers and customers may have rights under the law and be able to opt-out. So, the answer will be D as we know that, the Privacy Rule demands thou to provide a note to each of your "customers" regarding your privacy systems.
Answer: True
Explanation:
When a project manager is confronted with resource overload, an activity that is not on the critical path can be delayed in order not to unnecessarily delay the project. The non-critcal activities can be delayed than an amount no longer than the slack period. This levels demand for that worker.