Answer:
already subsribed , asha hi jiwan hai channel
Answer:All about Early Start, Early Finish, Late Start and Late Finish
This topic is very important from PMP exam perspective. You must expect a question or two based on the calculations of Early Start and Finish and Late Start and Finish.
Also, before we get into the details, it is very important that you have the understanding of the previous concepts that build up this topic, specifically the 3 listed below,
Network Diagrams
Critical Path
Float / Slack
Now, we already know that Float or Slack is the amount of time an activity can be delayed without impacting the project end date. But the early start or early finish and late start or late finish numbers can actually show you how much freedom you really have.
Early Start – The earliest time that an activity can start
Early Finish – The earliest time that an activity can finish
Late Start – The latest time that an activity can start
Late Finish – The latest time that an activity can finish
Each activity in Network Diagram is represented as below,
Explanation:
Answer:
Given that,
Direct materials = $100,000
Direct labor = $125,000
Applied factory overhead for Department 1 = $150,000
Direct materials = $50,000
Direct labor = $60,000
Applied factory overhead for Department 2 = $70,000
Therefore, the journal entry is as follows:
Work in Process - Department 3 A/c Dr. $555,000
To Work in Process - Department 2 $555,000
(To record the flow of costs into Department 3 during the period)
Workings:
Work in Process - Department 3:
= $100,000 + $125,000 + $150,000 + $50,000 + $60,000 + $70,000
= $555,000
Answer:
the self-employment tax is $7,065
Explanation:
The computation of the self-employment tax is given below:
Given that
net profit = $50,000
Now the 92.35% of net profit is $46,175
As it is lower than $128,400
So,
= 15.3% of $46,175
= $7,065
Hence, the self-employment tax is $7,065