Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.
Answer:
-4.3 degrees
Step-by-step explanation:
if I understand the problem correctly, then the temperature at midnight fell 15.7 degrees from 11.4 degrees at noon.
11.4 - 15.7 = -4.3 degrees
so, the temperature at midnight was -4.3 degrees
Teachers and principles probably still want to keep school a little old fashioned while still having little technology by the next year or 2 we'll might not have to carry heavy backpacks anymore I wish you the best of luck.
Answer:
DF^2=DH^2+HF^2
DF=√DH^2+HF^2
DF=√2(DH^2) {AS IT IS A CUBE THEN ALL SIDES ARE EQUAL}
DF=√2*11^2 {ALL SIDES OF A CUBE ARE EQUAL}
DF=√2*121
DF=√242
DF=15.555
THEREFORE,OPTION B..