they receive 25 per entry but 5 goes towards the cost of the race
so 25-5 = 20 per entry is for the charity
so 20x + 5000 = 25000
subtract 5000 from each side
20x= 20000
divide both sides by 20
x = 20000/ 20
x = 1000
they need at least 1000 entries to make 25000
so to make more than 25000, they need 1001 entries
There is no defined question so I'm just going to try my best.
If you are looking for which is a better deal between $4 for 16 and y=0.22x then the answer would be y=0.22x
If you place 16 ounces for "x" in the expression y=0.22x then the cost of the turkey or "y" would be $3.52
Answer: the due date would be 92 weeks
Step-by-step explanation:
Since the time required to complete a project is normally distributed, we would apply the formula for normal distribution which is expressed as
z = (x - µ)/σ
Where
x = number of weeks.
µ = mean
σ = standard deviation
From the information given,
µ = 80 weeks
σ = 10 weeks
If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, the z score corresponding to 90%(90/100 = 0.9) is 1.29
Therefore,
1.29 = (x - 80)/10
x - 80 = 1.2 × 10
x - 80 = 12
x = 80 + 12 = 92