Workers Days
2 42
3 28
6 14
12 7
Use the relationship in the table to complete the statements.
Select the correct answer from each drop-down menu.
As the number of workers increases, the number of days it will take to complete the project ________. The ______ of the two variables is constant.
The number of days it takes for a construction project to be completed varies ____ as the number of workers assigned to the project.
1 answer:
Which one of the following items does not appear under the heading 'equity and reserves' on a company
statement of financial position?
A Share premium account
B Retained earnings
C Revaluation surplus
D Loan stock
You might be interested in
Answer:
x=− 7 over 2 =−3.500
Hope this helps!
The anwser to the problem is C.
Given:
Depth, h= 15.8
Density of seawater= 1030kg/m3
We need to find:
Pressure
Answer:
P= ρhg
P=(1030)(15.8)(9.81)= 159647.94 Pa
Answer:
600 gallons
Step-by-step explanation:
10÷20=0.5
0.5 x 1,200=600 gallons
Answer:
Estimate: $900.00
Step-by-step explanation:
This cannot be A, B, or C, as it won't make sense with the increase of 75$ each 4 years, with 30K down payment,