Answer:
It's negative correlation, I took the test before going on summer break so I hope this helps <3 If you have anymore questions please feel free to ask!
Answer:
16 units
Step-by-step explanation:
graph each point on a graph and it will form a rectangle and then count the units around the rectangle and add them up and you get 16 units
Answer:
he is an ordinary man because that is what the speaker is talking about
Answer:
The three unknown angles X, Y , and Z are:
X = 40, Y = 20, and Z = 120
Step-by-step explanation:
Let's name X the measure of the first angle, Y the measure of the second one, and Z that of the third one.
Then we can create the following equations:
X = 2 Y
Z = 100 + Y
and
X + Y + Z = 180
So we use the first equation and the second one to substitute for the variable X and Z in the thrid equation:
2 Y + Y + (100 + Y) = 180
4 Y + 100 = 180
4 Y = 80
Y = 80/4 = 20
Then X = 40, Y = 20, and Z = 120
Answer: 8 minimum work stations is what would be needed.
Step-by-step explanation:
The cycle time is computed as the operating time daily divided by the scheduled output.
It is important to note that the daily capacity of the operation layout is the operating time divided by the cycle time.
Therefore,
If you need to produce 30units/hour.
The average cycle time is as follow:
The average cycle time is the average time between the completions of units.
60/30= 2 average cycle time
=16/2
=8
8 work stations is the minimum number that would be needed.
It is important to know that in an assembly line balancing, the minimum number of work station is the ratio of the sum of all tasks time to the cycle time.