The highest number that both 9 and 27 can be multiplied into is 9. 9 can go into 9 one time, and 9 can go into 27 three times.
9•1=9
9•3=27
(9, 18, 27 )=times
I hope I helped.
Solution: Estimated time for the work is 40 hour work week.
Estimated payment to 3 laborers working 40 hours at cost $14 per hour is:
$1680
Estimated payment to 6 masons working 40 hours at cost $24 per hour is:
$5760
Estimated cost of material = $3143
Contractor wishes to make a profit of $500
Therefore, the mathematical expression that will give the estimated cost of the job is:

The estimated total cost is:
Cost =$11083
8 feedings because she recorded it two times and giant humming Bird fed it 4x so 4×2=8
Answer:
bro use air math it will give u the answers trust me