Answer: See explanation
Explanation:
The increase in income for Spendia will be:
= 1 / (1 - MPC)
where MPC = 0.8
= 1 / (1 - 0.8)
= 1 / 0.2
= 5
Increase in income = Gross investment × multiplier
= $100 × 5
= $500 million
The increase in income for Savia will be:
= 1 / (1 - MPC)
where MPC = 0.5
= 1 / (1 - 0.5)
= 1 / 0.5
= 2
Increase in income = Gross investment × multiplier
= $100 × 2
= $200 million
Answer:
NPV =$ 60,311.80
Explanation:
<em>The net present value (NPV) of a project is the present value of cash inflow less the present value of cash outflow of the project.</em>
NPV = PV of cash inflow - PV of cash outflow
We can set out the cash flows of the project using the table below:
0 1 2 3
Operating cash flow 136,000 136,000 136,000
Initial cost (274,000)
Working capital (61,000 ) 61,000
Salvage value <u> </u> <u> </u> <u> </u> 1<u>5000 </u>
Net cashflow <u> (335,000) 136,000 136,000 212,000.</u>
PV inflow= (136000)× (1.1)^(-1) + (136,000× (1.1)^(-2) + (112,000)× (1.1)^(-3)
= 395,311.80
NPV =395,311.80 -335,000
=$ 60,311.80
Answer:
If we made the assumption that both countries had a per capita of $15,000 in 1960, country A, which entered an era of political stability, and applied liberal reforms, growing at a rate of 5%, would double its GDP per capita by 1975, reaching a GDP per capita of $31,183.92.
On the contrary, country B, which continued to grow by 1% per year, would only double its GDP per capita by 2030, reaching a figure of $30,101.45.
Therefore, it would take 55 years more for country B to double its per capita GDP level compared to country A.