Answer:
Optimistic duration
Explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration
Answer:
i would say Plane, if not then Plane then the person's birthdate.
Explanation:
which question are u referring too
Answer:
a. Systems testing
Explanation:
According to my research on information technology, I can say that based on the information provided within the question the term being defined is called System Testing. Like mentioned in the question, this is a technique used in order to evaluate the complete system the system's compliance against specified requirements, which tests its functionalities from an end-to-end perspective in order to evaluates patches used to close software vulnerabilities and make sure it complies with all policies.
I hope this answered your question. If you have any more questions feel free to ask away at Brainly.