Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer: 6
Step-by-step explanation:
i think joshira makes 6 item in 8 hours.
i got my answer by multiplying 3/4 with 8
• Imagine we are using these two points to draw a triangle where new point E is a right angle with coordinates (-1, -9)
• FE = 5
• EC = 4
• FE^2 + EC^2 = FC^2
• (25) + (16) = 41 = FC^2
• FC = square root(41)
x+5= 10
move +5 to the other side
sign changes from +5 to -5
x+5-5= 10-5
x= 10-5
x= 5
Answer:
x= 5