First, find out how much each man works. If eight men take 10 days to build 150 m of wall, then that means that it takes 80 man days to build 150 m. One Man day is then 150÷80, in other words 1.875. If eight men have already been working for six days, then they have spent 8×6 man days, 48. 48 men days times 1.875 m of wall per man day equals 90 m of wall have been built. So, you have four days left to build the remaining 60 m of wall as well as 45 extra meters, in other words, 105 m total. 105 m divided by four days equals 26.25 m need to be built every day. Since one man builds 1.875 m of wall every day, to find the number of men total you need for the last four days, take 26.25÷1.875, Which equals 14 exactly. 14 is not the answer however, because it’s asking how many more men you need. Since you already have eight, you need six more to make 14
The answer is six more men
Answer:
10.5
Step-by-step explanation:
225÷21.50
=10.46511
=10.5(3sf)
Answer:
see the explanation
Step-by-step explanation:
Let
x ---> kilograms of cement needed
y ----> kilograms of sand needed
z ----> kilograms of gravel needed
we know that
----> 

Divide 480 by 8
----> scale factor
Multiply the scale factor by the ratio 
<em>Find out the kilograms of cement needed</em>

<em>Find out the kilograms of sand needed</em>

<em>Find out the kilograms of gravel needed</em>
