Answer:
a) Product G should be produced and sold
b) Net financial advantage $80
Explanation:
<em>A company should process further a product if the additional revenue from the split-off point is greater than than the further processing cost. </em>
<em>Also note that all cost incurred up to the split-off point are irrelevant to the decision to process further . </em>
$
Revenue after split-off point
($9× 40 litres) 360
Revenue at the slit of point
($4 × 40) <u> (160)</u>
Additional income from further processing 200
Further processing cost ($3× 40) <u>(120)</u>
Incremental income from further processing <u> 80</u>
Incremental income from further processing = $80
a) The product F should be processed further and sold as product G. Doing so would increase the net income by $80.
b) Net advantage $80
Answer:
let your employer know how much to take out of your paycheck for taxes file a tax return
Explanation:
The W-4 Form or the Employee's Withholding Allowance Certificate, must be completed by new employees and its main purpose is to let their employer know how much federal taxes must be withheld form the employee's paycheck. Employers no longer have to routinely submit W-4 Forms to the IRS.
In their simplest form, bonds are pure a) debt.
<h3>What are bonds?</h3>
- A bond may be a debt security, almost like an IOU.
- Borrowers issue bonds to boost money from investors willing to lend them money for a certain amount of time.
- When you buy a bond, you're lending to the issuer, which can be a government, municipality, or corporation.
- In return, the issuer promises to pay you a specified rate of interest during the lifetime of the bond and to repay the principal, also referred to as face value or par value of the bond, when it "matures," or comes due after a group period of time.
<h3>What sorts of bonds are there?</h3>
The main types of bonds are:
- Investment-grade
- Corporate bonds
- Municipal bonds
- High-yield bonds
To learn more about bonds: brainly.com/question/17405470
#SPJ4
Answer:
Crash the schedule.
Explanation:
Fast-track can complete the task earlier but takes more money. Assign more experienced people will cost the management more money. Cut scope reduces the project requirement and finishes the task earlier. Therefore, options A B and D can not be the answer.
Crash the schedule (option C) is the answer because it allocates enough resources to complete the task earlier without spending more money.
The complete question should have been:
Malcolm Industries recently hired a large number of workers for the company's new construction factory in Colorado. During the hiring process, the management made a clear effort to recruit physically strong individuals because the work at the factory involves manual labor. The jobs need to be performed by individuals who have the energy and physical stamina to work for long hours. Which of the following surface-level characteristics did the company most likely concentrate on when selecting the new workers?
A.) Age
B.) Values
C.) Beliefs
D.) Religion
E.) Personality
Answer: Age.
Explanation:
Malcolm Industries made use of Age as the Surface Level Characteristic that determined who would be employed. A surface level characteristics can be defined as differences that individuals possesses that easily be identified when they are seen.