Answer:
Base Machines
Unit Cost = $25,848
Total Cost = $10,339,200
Treadmills
Unit Cost = $20,525
Total Cost = $5,131,250
Explanation:
<u>Base Machines </u>
<u>Unit Cost</u>
Machine hours (700 × $28) $19,600
Direct labor hours (182 × $20) $3,640
Setups (20 × $75) $1,500
Inspections (10 × $30) $300
Production orders (30 × $12) $360
Purchase orders (56 × $8) $448
Total Unit Cost $25,848
Units produced 400
Total activity cost (400 × $25,848) $10,339,200
<u>Treadmills </u>
<u>Unit Cost</u>
Machine hours (600 × $28) $16,800
Direct labor hours (64 × $20) $1,280
Setups (15 × $75) $1,125
Inspections (16 × $30) $480
Production orders (20 × $12) $240
Purchase orders (75 × $8) $600
Total Unit Cost $20,525
Units produced 250
Total activity cost (250 × $20,525) $5,131,250