This statement is false. The loan period does get to affect the total cost of the loan. Loans tend to have an annual percentage rate applied to it when you had it. It is a term used to refer the interest rate of the loan you had acquired.
The court system is messed up i dont get what you are asking.
<u>Teardrop Rucksack</u> has the highest production cost.
Production fees refer to all of the direct and oblique fees businesses face from production a product or offering a carrier. Manufacturing expenses can consist of a selection of costs, including exertions, raw substances, consumable manufacturing materials, and general overhead.
It includes 3 most important costs: uncooked substances, direct labor, and overhead. Those charges can be fixed (maximum overhead) or variable (uncooked substances and hard work). The whole product value formula is general Product price = fee of raw substances + price of Direct exertions + price of Overhead.
Blanketed inside the production fee are (1) the fee of uncooked materials, (2) the fee of direct labor, and (3) the cost of overhead. Raw substances and hard work costs are frequently variable, even as the overhead expenses are in the main fixed.
Learn more about production cost here:- brainly.com/question/13738783
#SPJ4
Answer:
Variable overhead rate variance = $ 875 favorable
Variable overhead efficiency variance = $ 4,185 favorable
Variable overhead cost variance = $5,060 Favorable
Explanation:
Standard hours = 1 hr x 2600 units = 2600 hours
Standard rate = $3.10
Actual hours = 1,250 hours
Actual rate = $2.40
Variable overhead rate variance = ( Standard Rate - Actual Rate ) x Actual Hrs
= ( $ 3.10 - $2.40 ) x 1250 Hrs
= $0.7 x 1250
=$ 875 favorable
Variable overhead efficiency variance = (Standard hours - Actual hours) x Standard Rate
= (2600 - 1250 ) x $ 3.10
= $ 4,185 favorable
Variable overhead spending variance = Variable overhead rate variance + Variable overhead efficiency variance
= $875 + $4,185
= $ 5,060 favorable
Variable overhead cost variance = Standard cost - Actual Cost
= (2600 X 3.10) - (1250 X 2.40) = 8,060 - 3000
= $5,060 Favorable