Answer would be .24, according to my "calculations"
Answer: Puresource Pharma would have to reduce it's cost
Explanation:
Horizontal integration could be defined as the merge between two or more companies that carry out similar functions or market in production.
Puresource Pharma would have to reduce it's cost of product and either sell below or same cost as their acquired company's product. This would help promote her market and would give a monopoly for them for the market for both of them.
Answer:
The correct answer is D
Explanation:
Under the doctrine of the stare decisis, the court will look into the past or the similar issues in order to guide their decisions related to the issues. And the past decisions are referred or acknowledged as the precedent.
Precedent is the principle or rule which is legal and it is established or created by the decision of the court. And this decision become the authority or the example for judging or deciding the similar issues.
Therefore, in this case, the trial court when deciding upon the case of D v E, will likely to allow or permit the minor to cancel the contract or the agreement.
Answer:
The correct answer is True.
Explanation:
The steps to follow to create a work breakdown structure are as follows:
1. Organize a meeting and share with the main stakeholders: team members are one of the most valuable assets in the process of creating the work breakdown structure. They have the knowledge, experience and creativity necessary to define each deliverable reaching the most specific details.
2. Complete the definition of all project deliverables: it is about going one step beyond the level reached in the planning and 100% complete the information on all project deliverables, including internal and external, associating each one with its estimated completion time.
3. Break down each deliverable into smaller, more manageable parts: it is about achieving a realistic level of work planning by the project manager, which ensures that, without interfering with the total estimated project deadline and the overall plan, it can be completed by the work teams. It is about determining work packages. These units constitute the lowest level of the EDT and are pieces of work that are specifically assigned to a person or a team of people to be completed, under the supervision of the Project Director. It is recommended that they focus on a single point of responsibility. The work packages will be used later to define the activities and tasks in which the project is divided.
4. Review the results obtained: with the stakeholders, both at the time of finalizing the elaboration of the work breakdown structure, and when modifications or updates are included, if applicable. It is essential to avoid overlaps.