No it is not because it is 47,000
Multiply both sides by 4
subtract 24r from both sides
simplify r - 24r to -23r
divide both sides by -23
two negatives make a positive
simplify 14/5/23 to 14/5 x 23
simplify 5 x 23 to 115
switch sides
Answer: r = 14/115.
Answer:
A: sqrt(11)
B: 4.2
C: sqrt(26)
Step-by-step explanation:
First, 4^2 = 16
That means that sqrt 11 is smaller than 4.2 (a value greater than 4). This is because sqrt16>sqrt11.
Sqrt(26) is greater than sqrt(25) = 5. That means that it's greater than 4.2.
Hence, the order given above.
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished