Answer:
"Problem recognition" is the correct answer.
Explanation:
- An empirical investigation has said that the initial phase of the development procedure of the customer and therefore its approach to buying seems to be the acknowledgment of problems that arise when consumers realize that perhaps the problem would also have to be solved.
- This is whenever the customer sees a requirement and is driven to rectify the conflicts.
Answer:
process control systems, human resource management systems, sales and marketing systems, inventory control systems, office automation systems, enterprise resource planning systems, accounting and finance systems and management reporting systems.
Explanation:
Is that the question or what i need info.XD
Answer:
$160 overapplied
Explanation:
Icy Mocha company estimates it's factory overhead costs to be $35,000 and machine hours to be 5,000 for a period of one year.
The actual number of hours worked on job 333 and 334 equals a total of 4,980
The actual factory overhead costs are $34,700
The first step is to calculate the predetermined overhead rate
= Overhead costs/machine hours
= $35,000/5,000
= $7
The amount of either over or underapplied factory costs can be calculated as follows
= predetermined overhead rate×actual number of hours worked
= $7×4,980
= $34,860
The amount is then subtracted from the actual overhead costs
= $34,700-$34860
= -$160
= $160 overapplied
Hence the amount of overapplied factory overhead is $160
Answer:
9 kanban
Explanation:
The calculation of the number of kanban containers needed is given below:
= (Lead time demand + Safety stock) ÷ kanban size
where,
Lead time demand is
= 1,500 radios × 1 days
= 1,500 radios
Container size = 250 radios
Safety Stock is
= 1 ÷ 2 day × 1,500 radios
= 750 radios
So, the number of kanban containers needed is
= (1,500 radios + 750 radios) ÷ (250 radios)
= 9 kanban
We simply used the above formula to find out the required kanbans