Answer:
a. (AR-SR)* Actual hours = Labour rate variance
Actual rate = (-3,850/2,750) + $17.60
Actual rate = -$1.4 + $17.60
Actual rate = $16.20
b. Direct labour efficiency variance for August = Total direct labour budget variance - Direct labour rate variance
= 1,430 - (-$3,850)
= $5280 Unfavourable
c. Direct Labour efficiency variance = (AH-SH)*SR
5280 = (2,750 - SH) * 17.60
(2,750 - Standard hours) = 5280/17.60
(2,750 - Standard hours) = 300
Standard hours = 2,750 - 300
Standard hours = 2,450
marci, a purchasing agent, orders 300 refrigerators per month from an online vendor portal. in doing so, she has made Operational decision.
operational judgments
Operational decisions, which typically have effects for no more than a year or even a day, are those that are altered more frequently in accordance with the current external and internal situations. The scale, complexity, and formulation of optimization models for operational decisions vary greatly as a result of the vast number of operations that make up the BSC. Operational choices related to biomass acquisition operations include logistics for carrying harvested biomass to storage, scheduling of working shifts, designating harvesting operation regions, and assigning personnel to harvesting machines. In terms of inventory management operations, it is necessary to regularly decide how much needs to be replenished from the upstream, delivered to the downstream, used to make biofuel goods, and stored in storage facilities.
to know about operational decisions
brainly.com/question/1266027
#SPJ4
Answer:
<u>Price per share of MGDI's stock is $78</u>
Explanation:
Earnings per share=Total earnings/Shares of common stock outstanding
=(13/2)=$6.5
PE ratio=Stock price/Earnings per share
Stock price=$6.5*12
=$78.
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.