1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
choli [55]
3 years ago
9

Rosa bought a storage container in the shape of a cube to store clothes. The storage container has a volume of 950 cubic inches.

What is the length of one side of the storage container? Estimate the length to the nearest integer.
Mathematics
1 answer:
vichka [17]3 years ago
8 0

Answer:

<h3>10in</h3>

Step-by-step explanation:

The volume of a cube is expressed as;

V = L³

L is the length of one side of the cube

Given

V = 950in³

Required

Length of one side of the cube

Substitute the given parameters into the formula and get L as shown;

V = 950in³

950 = L³

Take the cube root of both sides

∛950 = ∛L³

∛950  = L

L = ∛950

L = 9.83

Hence the length of one side to nearest integer is 10 inches

You might be interested in
Solve a triangle when A=40 B = 50 , and C=14.
tekilochka [14]

Answer:

(c)=81°, a=9.1, b=12.

Step-by-step explanation:

m<A=40°, m<B=59

m<C=180-(40+59)=81

c=14

6 0
3 years ago
It takes 15 electricians 24 days to wire a new housing subdivision. how many days would 18 electricians require to do the same j
Romashka [77]
15 electricians worked for 24 days to the whole job, now, there are 15 of them, so on any given day, each electrician worked one whole day, in 24 days, that one electrician worked 24 days total.

now, there were 15 electricians on any given day though, since each one of them worked the whole day that one day, so the "days work worth" on a day is 15, so the house gets 15days worth of work because of that.

so how many "days worth" did all 15 do on the 24 days, well, 15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15, namely 15 * 24, or 360 days worth of work.

since it takes 360 days worth of work to do the whole wiring, in how many days would 18 electricians do it?   360/18.
4 0
4 years ago
Read 2 more answers
Plz help plz I am already failing I dont want to fail more
Gnom [1K]

Answer:

B is the closet to pi hsiebfjwjgsbe9fbe

7 0
3 years ago
Excel remembers the last _____ actions you have completed. 25 50 75 100
Gemiola [76]
Excel remembers the last 100 actions you have completed.

Microsoft Excel or MS Excel is a spreadsheet developed by Microsoft. It is used in Windows, Mac OS X, iOS, and Androids. It features calculation, pivot table, graphing tools, and macro programming language. 
5 0
4 years ago
Help asaap dont use me for points please
denpristay [2]

Answer:

-1.5

Step-by-step explanation:

You were on the free points page

6 0
3 years ago
Other questions:
  • The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. Th
    13·1 answer
  • A light bulb consumes 3600 watt-hours per day. How long does it take to consume 17100 watt-hours?
    9·1 answer
  • If Carol hangs a picture
    15·2 answers
  • Solve the equation. -2x + 7x + 34 = -2 ( 1 - 7 \x )
    7·1 answer
  • Write 11/39 in lowest terms
    7·1 answer
  • Tell whether the angles are adjacent or vertical. Then find the value of x.
    9·1 answer
  • A mistake was made in the steps shown to simplify the expression. Which step includes the mistake?
    11·2 answers
  • Mason is insane on the basketball court. He has 15 games left. How many more games do you expect him to score 13-15 points?
    8·1 answer
  • PLZ HELP IM BEING TIMED!!!
    5·1 answer
  • How to divide like that
    6·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!