Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Answer:
The correct answer is (d) email.
Explanation:
Email is a form of written communication between people through digital tools. Also called email or e-mail (for its meaning in English electronic mail), it is one of the most popular means of digital communication and can be used by anyone who has access to the internet.
In this case, Bob must use a means of communication that ensures that he will not interrupt his boss's meeting. In addition, it is practical because an immediate response can be given without having to pass authority filters.
Firms can raise the financial capital they need to pay for such projects in four main ways: (1) from early-stage investors; (2) by reinvesting profits; (3) by borrowing through banks or bonds; and (4) by selling stock. When owners of a business choose sources of financial capital, they also choose how to pay for them.
ummmm I ain't sure if this is the answer you need please read properly before you write
It is c ..........................................................................................................................................................................