1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Paul [167]
3 years ago
9

ABC and DEF are congruent triangles. Which of the following is known to be true?

Mathematics
1 answer:
Anna11 [10]3 years ago
4 0

If in triangles ABC and DEF, AB = DE, AC = DF, and angle A = angle D, then triangle ABC is congruent to triangle DEF. Using words: If 3 sides in one triangle are congruent to 3 sides of a second triangle, then the triangles are congruent.

You might be interested in
What is the surface area of this figure?
Korvikt [17]

Answer: it’s 400

Step-by-step explanation:

6 0
3 years ago
a bag contains 5 red marbles 4 blue marbles and 6 yellow marbles if 3 marbles are selected in succession what is the probability
Alex

Answer:

5/243

Step-by-step explanation:

4/18 × 6/18 × 5/18 = 5/243

I think

6 0
4 years ago
What is the rule that defines the function shown in the graph for the interval, {-2 < x < 0}?​
KIM [24]

Answer:

Step-by-step explanation:

720,080 in expanded form with components

(7 X 10>50

3 0
3 years ago
Rewrite the numbers from least to greatest 0.33,-0.12,-0.127,0.2,45/10
Sonbull [250]
-0.127
-0.12
0.20
0.33
45/10
I think that is right
8 0
3 years ago
Read 2 more answers
Which EST graph correctly represents the information on the table ​
garik1379 [7]

Answer:

  the first one

Step-by-step explanation:

A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.

The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.

The second graph does not appropriately account for duration of predecessor tasks.

The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).

3 0
3 years ago
Other questions:
  • Plz answer it fast I will give you ten point
    6·2 answers
  • joe needs to cut a piece of sheet metal into 5 pieces. it takes him 2 minutes to make each cut. how many cuts will joe make?
    12·2 answers
  • Three more than 4 times a number
    12·1 answer
  • {HELP ASAP }WILL GIVE 50+ POINTS AND BRAINLIEST
    14·1 answer
  • K/2 + 1/2 = 3 what does the k=
    7·1 answer
  • You want to take a two hour airboat tour. its $35 for a boarding fee and $5 per half hour. Write a function that represents the
    9·1 answer
  • Divide. Write your answer in simplest form.<br> 7/10 divided by 5/16
    6·1 answer
  • Graph the linear equation y= 1/2x
    7·1 answer
  • Ms salazar car average 25 miles per gallon of gasoline she filled the 10 gallon tank with gasoline before traveling 200 miles
    14·1 answer
  • Can someone help me in the two questions
    14·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!