Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.
Answer: Create a sales plan that aims to enhance initial sales and market penetration with low prices based on high operational costs.
Explanation:
An emerging market is the economy of acountru that's developing and therefore,.such country is becoming more engaged with the global markets due to its growth and expansion as it grows.
The advise that'll be given to Patagonia to omit from consideration in crafting a strategy to enhance future profits in these two emerging markets is to create a sales plan that aims to enhance initial sales and market penetration with low prices based on high operational costs.
Answer:
Loss on disposal $1,800
Explanation:
Cost of Asset 26,000
Useful life 5years
Sale proceeds 19,000
Depreciation for the year=$26,000/5=$5,200
Written Down value(WDV)=$26,000-$5,200=$20,800
Loss on Disposal= Sale proceeds- WDV=$19,000-$20,800=$1,800
It is assumed that depreciation is fully charged for the year on asset.
Answer:
Answer is option b i.e. will produce a plan that may not be the best plan.
Explanation:
Simulation is the technique used to create an artificial environment that is similar to the real-life situation to study various problems and how to tackle them. However, it is not the full proof plan which means it is based on certain probability and chances that a certain situation might arise. Many times situations are not as planned and here we cannot solely depend on the solution that we have learned during the simulation process. Therefore, the simulation will provide us with a plan that may or may not be the best plan.