Answer:
x = 9.2
Step-by-step explanation:
The answer is math+math=math
Answer:
stress on the cable is 61.312mpa
If steel is used, extension will be 0.91968mm
If polypropylene is used, extension will be 0.1532mm
Step-by-step explanation: detailed explanation and calculation is shown in the image below
Answer:
D
Step-by-step explanation:
25% of 16 is 1/4x16=4, which leaves D as as your answer
Let x = the amount of time that the third person needs to work on the job to add up to one
1 = 1/2 + 1/3 + x
1 - 1/2 - 1/3 = x
To subtract the fractions we need to put them all over a common denominator. Let's use 3*2 = 6 as the denominator; so 1 = 6/6, 1/2 = 3/6, 1/3 = 2/6:
6/6 - 3/6 - 2/6 = x
1/6 = x
The third person must work 1/6 time on the project.