Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
If a monopolist or a perfectly competitive firm is producing at break-even point then they're basically equaling their average revenue to the average total cost - ii.
This basically means that they are operating at a level where the amount which they produce relates to the amount they spend.
Answer:
B. $6
Explanation:
Marginal revenue for the worker = change in wage ÷ change in quantity output
Change in wage = (40×$6) - (36×$6) = $240 - $216 = $24
Change in quantity output = 40 - 36 = 4
Marginal revenue for the worker = $24 ÷ 4 = $6