Answer: 1. $690 (favorable)
2. $9045 (favorable)
Explanation: These can be computed as follows :-
Labor rate variance = Actual labor cost - (standard rate * actual hours)
= $139,380 - ( $20.1 * 6900 hours )
= $690 (favorable)
.
Labor efficiency variance = ( Actual hours - standard hours ) * (standard rate )
= [6900 hours - (1500 units * 4.3 hours) ] * ($20.1)
= $9045 (favorable)
Answer:
The multiple choices are
a. $240,000
b.
$228,000
c.
$216,600
d.$205,770
e.
$0
The correct option is E,$0
Explanation:
The funding required from equity is 40% of the projected capital budget of $2000,000 which is expected to be from the profit attributable to stockholders since new issue of shares is not contemplated.
In other words, dividends payable to shareholders is the net income less their counter funding of the project which is computed below:
residual dividends=net income-(equity%*capital outlay)
residual dividends=$300,000-(40%*$2000,000)
=$300,000-$800,000=$0
In essence the $300,000 is not even enough as funds expected from equity less alone paying excess as dividend
Answer: True
A chronological resume lists your work history in order of of date.
Answer:
$100,340
Explanation:
<em>The amount of cost recorded in the asset account would be:</em>
List price $93,000
Less: Discount ($93,000*2%) $1,860
Add: Freight $3,800
Add: Installation&Testing <u>$5,400 </u>
Cost of the machine <u>$100,340</u>
Note: Insurance cost is not included in the cost of the machine