Answer:
c. $74,450
Explanation:
The computation of the Net present value is shown below
= Present value of all yearly cash inflows after applying discount factor + salvage value - initial investment
where,
The Initial investment is $120,000
All yearly cash flows would be
= Annual net operating cash inflows × PVIFA for 6 years at 14%
= $50,000 × 3.8887
= $194,435
Refer to the PVIFA table
Now put these values to the above formula
So, the value would equal to
= $194,435 - $120,000
= $74,435 approx
Answer:
c
Explanation:
The federal reserve systems responsibilities include influencing the supply of money and credit to banks
To record the write-off of receivables:
Allowance for doubtful accounts ----------------------------$24,000
Accounts Receivable -----------------------------------------------$24,000
To record the accounts receivable collected from the written-off receivable, first restore the accounts receivable with the following entry:
Accounts Receivable ------------------------------------------$1,900
Allowance for doubtful accounts ------------------------------$1,900
To record the collection of accounts receivable:
Cash -----------------------------------------------------------------$1,900
Accounts Receivable ----------------------------------------------$1,900
Or, the direct journal entry to record the collection of previously written-off accounts receivable is:
Cash ---------------------------------------------------------------$1,900
Allowance for doubtful accounts ------------------------------$1,900
Deposit column. You can also state in the comments section that it was interest earned from the checking account.
Answer:
$2,880
Explanation:
Given that,
Total machine-hours = 30,300
Total fixed manufacturing overhead cost = $ 575,700
Variable manufacturing overhead per machine-hour = $ 4.00
For Job T687:
Number of units in the job = 10
Total machine-hours = 30
Direct materials = $730
Direct labor cost = $1,460
Total variable overhead estimated:
= Variable manufacturing overhead per machine-hour × Total machine-hours
= $4 × 30,300
= $121,200
Total overhead estimated:
= Total variable overhead estimated + Total fixed overhead estimated
= $121,200 + $575,700
= $696,900
Predetermined overhead rate:
= Total overhead estimated ÷ Total machine-hours
= $696,900 ÷ 30,300
= $23 per machine hour
Total overhead applied:
= predetermined overhead rate × Total machine hours for Job T687
= $23 × 30
= $690
Total job cost:
= Direct material + Direct labor + Total overhead
= $730 + $1,460 + $690
= $2,880