The epa tries to balance protecting business interests with protecting the environment. EPA stands for Environmental Protection Agency. It <span> is an </span>agency<span> of the Federal government of the United States which was created for the purpose of </span>protecting <span>human health and the </span><span>environment.</span>
Answer:
a) direct labor cost for job order costing and machine hours for process costing.
Explanation:
As we know that the predetermined overhead rate is the rate which is to be computed by considering the total estimated manufacturing overhead cost and the estimated activity level i.e machine hours, etc
Under the traditional costing, in case of job order costing it ts based on direct labor cost while in the process costing it is based on machine hours
Hence, first option is correct
Answer: C. grant Mary the legal rights for the property.
Explanation:
Agents are not to use the knowledge that their principal paid them to acquire or that they acquired for the use of their principal for themselves.
If Mary bought a property knowing that Karen wanted to buy that property, the Court will award the title to Karen because Mary has violated her duty not to use knowledge of information intended for her principal for her own benefit.
In a project network, the critical path is the sequence of activities which has the longest time. A series of interconnected tasks known as the critical route has a direct impact on the project's completion date.
<h3>What do you men by the project network?</h3>
A project network is a graph that displays the actions, lengths of time, and dependencies among your project's tasks.
Techniques like Gantt charts, PERT charts, and critical path management can be used to form project networks. The project network has a number of paths, but each terminal piece must be located on just one of those paths.
A project's workflow is shown graphically in a project network diagram. A network diagram is a project management chart that lists boxes for activities and roles, followed by arrows that show the timetable and order in which the work must be done.
Therefore, in a project network, the critical path is the sequence of activities which has the longest time. A series of interconnected tasks known as the critical route has a direct impact on the project's completion date.