Answer:
B) Retaining
Explanation:
Retaining risk refers to the risk in which the company could able to take the decision with respect to the responsibility for some particular risk
Here in the given situation it represents that the risk is associated with one of the key members so this presents the responsibility that should be considered while retaining a risk
Hence, the correct option is B.
Answer:
The American Opportunity Tax Credit (AOTC) that can be claimed is $2,500.
Explanation:
As of 2018, no changes have been made to the AOTC. By law, with a modified adjusted gross income (MAGI) of $80,000 or less for single individuals and $160,000 or less for married filing jointly, the individuals can claim the full credit amount. It is a credit paid for an eligible student to cover education expenses, if in the first four years of postsecondary education. A maximum annual amount of $2,500 is given and an additional 40% of remaining amount (up to $1,000) if the tax owed falls to zero.
Answer:
The answer is True
Explanation:
The DC Kitchen which was started by Robert Egger was meant to address hunger by empowering minds and to meet the needs of those who were in poverty.
The design is shown in the attached picture. An equilateral triangle has sides that have equal measurements. On the other hand, a vertex is the terminal point of at least two line segments. Therefore, when you join three equilateral triangles sharing a common vertex, that simply means that they have a common point.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.