The best answer choice would be "B". This gives the main idea of what your debate would be about. It is also clear, and not biased or opinionated.
I hope this helps!
~cupcake
Answer:
General agent
Explanation:
A general agent is a person that the principal authorises to perform transactions in relation to a part business on a certain place.
A general agent can perform all acts in relation to a business that has been assigned by the principal. For example in real estate when an agent performs property management functions for his client he is acting as a general agent.
On the other hand a special agent is one that is employed by a principal to perform a specific task or job and his scope of responsibility is limited to that job function.
Answer:
$671,300
Explanation:
The calculation of adjusted basis in the building is shown below:-
Adjusted basis = Original cost of the property + Cost of capital improvements - Depreciation claimed
= $750,000 + $50,000 - $128,700
= $800,000 - $128,700
= $671,300
Therefore for computing the adjusted basis we simply add original cost of the property with cost of capital improvements and deduct depreciation claimed.
<span>Michael mixed three colors of paint and came up with black. this is an example of subtractive color mixing. When you mix together subtractive colors eventually the light is subtracted from them giving off a black color tone. These colors change with the light but can cancel each other out easily. </span>
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.