Answer:
240 hours
Step-by-step explanation:
One person hour is a unit indicating the rate at which one person is working on the project .
The company estimates that it will take 2880 person- hours to complete the job
So let's determine how many hours it will take 12 workers to complete same job
The rate = 2880 person/hour
12 persons or workers =( 2880 person/hour)/12 persons
12 persons or workers = 2880/12
12 persons or workers=240 hours
It will take 12 workers 240 person hour to finish the project.
Thank you
The division is using extra zeros.
2 * 16 = 32, but 3200 was placed below 3426.
Now 1 * 16 = 16, so 160 goes below 226.
The number that goes in the box is 160.
Answer:
Step-by-step explanation:
8b-4b+8-3=4b+5
4b=-5
b=-5/4=1 1/4
22-12=10
so this missing answer after the + is 10
Standard form of a circle" (x-h)²+(y-k)²=r², (h,k) being the center, r being the radius.
in this case, h=-2, k=6, (x+2)²+(y-6)²=r²
use the point (-2,10) to find r: (-2+2)²+(10-6)²=r², r=4
so the equation of the circle is: (x+2)²+(y-6)²=4²