PLEASE HELP ME ON MATH ASAP

Mathematics
2 answers:
Alchen [17]2 years ago
6 0

4

cause then 12-6=6

You do parenthesis first and get six, then you subtract

alukav5142 [94]2 years ago
5 0

Answer:

B i think

Step-by-step explanation:

Sorry if wrong

You might be interested in
You can replace any letter in function notation with any number.
Vikentia [17]
A. That would be True
5 0
3 years ago
Multiply. Write your answer in scientific notation.<br> (8.8 x 10')(7.5 x 10<br> 10 )
lana66690 [7]
6,666,00 Feet
Answer to you’re question
7 0
3 years ago
Justin and elena each launched a toy rocket into the air. the height of justin’s rocket is modeled by the equation h = –16t2 60t
mario62 [17]
I don’t know you just have to add and keep adding them
8 0
1 year ago
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be run
Alecsey [184]

Answer:

Scheduled Variance = $850,000.00

Schedule Performance Index = 1.05

Cost Performance Index = 1.11

Step-by-step explanation:

Note: See the attached excel file for the calculations of Total Actual Cost to Date, Budgeted Cost of Work Scheduled (BCWS), and Budgeted Cost of Work Performed (BCWP).

From the attached excel file, we have:

Total Actual Cost to Date = $15,300,000

Total BCWS = $16,170,000

Total BCWP = $17,020,000

Therefore, we have:

Scheduled Variance = Total BCWP - Total BCWS = $17,020,000 - $16,170,000 = $850,000.00

Schedule Performance Index = Total BCWP / Total BCWS = $17,020,000 / $16,170,000 = 1.05

Cost Variance = Total BCWP - Total actual cost to date = $17,020,000 - $15,300,000 = $1,720,000

Cost Performance Index = Total BCWP / Total actual cost to date = $17,020,000 / $15,300,000 = 1.11

Download xlsx
7 0
2 years ago
Assume the monthly interest rate is 1/12 of the annual interest rate . you maintain an average balance of $450 on your credit ca
masya89 [10]

Answer:

The monthly interest payment would be $ 9

Step-by-step explanation:

Given,

The average balance of the credit card = $ 450,

Annual rate of interest = 24%,

∵ Monthly interest rate is 1/12 of the annual interest rate,

Thus, the monthly interest rate = \frac{1}{12}\text{ of }24\%

=2\%

Hence, the monthly interest payment = 2% of credit card balance

= 2% of 450

=\frac{2\times 450}{100}

=\frac{90}{10}

= $ 9

3 0
3 years ago
Other questions:
  • 10) Write an expression: the quotient
    7·1 answer
  • The length, L, of a steel rod is 7.36 m, correct to 2 decimal places. complete the error interval for,L
    13·1 answer
  • Kara buys 24 bagels. Ten are whole wheat. What fraction of the bagels are wheat? Write in simplest form.
    6·2 answers
  • Pls help i dont understand :( Will Give Brainliest + 25 points!!
    8·1 answer
  • Find equation of straight line which
    15·1 answer
  • The measure of an angle is 142.5°. What is the measure of its supplementary angle?
    7·1 answer
  • SOMEONE HELP ME PLSSSSSSSSSSSSSS
    11·1 answer
  • Show all work to identify the asymptotes and zero of the function f of x equals 6 x over quantity x squared minus 36.
    13·1 answer
  • City code says you need to have at least 50 toilet stalls, but each bathroom can only have 10 stalls. You need to have the same
    12·1 answer
  • What Values of X Makes these equations true?<br><br> Label Them as <br> 1.<br> 2.
    8·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!