Answer:
A store that buys a shipment of new computers cant afford to buy new phones.
Explanation:
Answer:
$663.420
Explanation:
The value for the investment is the future of $1000, earning a compound interest of -5% for eight years.
The formula for compound interest is as below.
FV = PV × (1+r)^n
Fv = $1000 x ( 1 + (-5/100)^8
Fv= $1000 x (1 +(-0.05)^8
FV= $1000 x (0.95)^8
Fv=$1000x 0.6634204
Fv=$663.420
The value will be $663.42
Answer:
The correct answer is schedule (time), budget (cost) and performance (resources).
Explanation:
To develop the Schedule, the outputs of the processes will be used together with the determined planning tool:
- Plan the Schedule Management. It consists of establishing the necessary policies, procedures and documentation. In order to plan, develop, direct and control the Project Schedule.
- Define the Activities. It consists of identifying those activities necessary to carry out the Project successfully.
- Sequence the Activities. It consists of identifying and documenting what kind of dependency exists between the different activities.
- Estimate resources of the Activities. It consists in estimating what type and amount of resources we need and are available to execute each activity.
- Estimate the duration of the Activities. It consists of establishing approximately how much time is necessary to complete each activity. As well as the number of resources estimated in the previous process.
- Develop the schedule. It consists in analyzing and integrating the order of execution of activities, their duration, resource requirements and possible restrictions. All this, integrated into the planned planning tool, will generate the Project Schedule, and with it the Baseline of the Schedule.
- Check the schedule. It consists of following the status of the Project, monitoring its progress and comparing with the baseline to manage possible changes.
The work necessary to carry out the six processes of Time Management must be preceded by a planning effort by the Project team, which is part of the process Develop the Project Management Plan. From it we will obtain, among others, the Schedule Management Plan that determines a methodology, the planning tool used, the format and the criteria to develop and control the Project Schedule.
------
NOTE: If you need to extend the explanation given, you can make a comment or add a new question. I will be very pleased to help you.
Assuming no economies of scale and identical costs, if the firms in a purely competitive industry were replaced by a profit-maximizing monopolist, the likely result would be <u>an Increase in price and reduced output</u>.
A key characteristic of a monopolist company is that it is a profit maximizer. A monopolistic market has no opposition, meaning the monopolist controls the rate and quantity demanded. the level of output that maximizes a monopoly's earnings is while the marginal cost equals the marginal sales.
The profit-maximizing monopolist for the monopoly will be to produce at the amount wherein marginal sales is equal to marginal fee: that is, MR = MC. If the monopoly produces a decreased amount, then MR > MC at those ranges of output, and the firm could make better income by way of expanding output.
The profit-maximizing output stage is represented as the only at which total sales is the height of C and total price is the peak of B; the maximal earnings is measured as the period of the section CB. This output level is also the only at which the whole earnings curve is at its maximum.
Learn more about monopolist here: brainly.com/question/13113415
#SPJ4