Answer: C) $2,000 per week.
Explanation:
The slope of the project refers to the additional amount that it would cost to be able to finish the project faster than schedule.
In the question, the construction activity is for 14 weeks at a rate of $5,000 for the laborers per week. If you wanted to reduce this project duration to 10 weeks, you will have to spend an additional $2,000 more per week.
This $2,000 is therefore the slope of the activity.
Answer:
Option C
Explanation:
Clearly placed, the right response is obvious through the sentence 'Harry assumes, on the another side, that any improvement in governmental expenditures will have a huge effect on GDP.' Comparison is made with the result with utilizing the economic management instrument, that is, budget expenditures and taxation.
Thus, from the above we can conclude that the correct option is C.
Answer:
a) Contribution from the special order= $52,640.
b) Stuart should accept the order
Explanation:
The amount of contribution to profit from the special order is the difference between the revenue and the relevant cost of variable cost of the special order.
The relevant cost of the special order is equal the sum of all variable cost only.
Note that the allocated facility overhead is irrelevant to whether to accept or reject the order. This is so because the costs would still be incurred either way.
Relevant variable costs of special order = (880 + 510) × 47 = $65,330
Sales revenue = 2,510 × 47 = $117,970.00
Contribution from the special order =$117,970.00 - $65,330
= $52,640.00
B) Stuart should accept the special order because it would increase its profit by $52,640.
Answer:
The rate of return on the risky asset is 16% and on treasury bill is 6% and we need a return of (1100-1,000)/1000= 10% or 0.1
If we think of x as the percentage investment in risky asset and 1-x as the investment in non risky asset we can mathematically find what proportion we need to invest in each asset to get this return.
16x+ 6(1-x)=10
16x+6-6x=10
10x=4
x=4/10
x= 0.4
This equation tells us that we should invest 40% in risky assets and 1-x which is 60% in treasury bills. We can test our answer by putting these values and see if the return is 10 %
(0.4*16)+(0.6*6)= Rate of return
Rate of return=10%
10% of 1000 = 100
100+1000=$1100
Explanation:
Answer:
The correct answer is letter "A": The company is on a tight deadline to complete a major project for an important client.
Explanation:
Coercion is the act by which a party forces to act another against its will because of a threat or an adverse situation. In the case given, as employees are underperforming, executives might find and excuse in an upcoming deadline of a major project for an important client to urge employees to hurry up in their jobs, otherwise the goal will not be met.