Answer:
This project should be rejected because the AAR is 10.68 percent.
Explanation:
The accounting rate of return of the project needs to computed,compared with the required accounting rate of return in order to decide whether the project should accepted or rejected:
Profit margin=$86,800*6%=$5208
Average operating assets=($97,500+$0)/2=$48.750
Accounting rate of return=profit margin/average operating assets*100
Accounting rate of return=$5,208/$48,750*100=10.68%
The project accounting rate of return is lower than the required accounting rate of return,hence the project should be rejected.
Answer:
See attachment for 1 and 2
Explanation:
Number 2 (continuation)
ISP should process the soy meal into soy cookies because that increases profit by $263. However, ISP should sell the soy oil as is, without processing it into the form of Soyola, because profit will be $56 higher if they do. Since the total joint cost is the same under both allocation methods, it is not a relevant cost to the decision to sell at splitoff or process further.
Answer:
The correct answer is (C)
Explanation:
Medical records do not come under the federal privacy act. A patient or a guardian can file a proper request for medical records and after proper identification medical records are released. The request should be a written application or signed by the patient himself. Congress, sec stock trading and FBI investigation are all exempted from federal privacy act.
Answer:
The NPV of the project is $974.
Explanation:
The net present value is the today's value of a stream of cash flows. The net present value will be the sum of all the expected future cash flows from a project less the initial investment required for the project and it is used to evaluate the investment decisions.
The net present value of an investment project will be:
NPV = CF1 / (1+r) + CF2 / (1+r)^2 + ... + CFn / (1+r)^n - Initial investment
or
If the cash flows are constant or of same amount through out, occur after the same interval of time and are for a defined period of time, they become an annuity and the NPV of such a project can be calculated by,
NPV = (Cash flow per period * Present value of Annuity factor) - Initial cost
The NPV of this project will be = (2000 * 2.4869) - 4000 = 973.8 rounded off to $974