Answer:
-$720 unfavorable
Explanation:
The computation of the material quantity variance is shown below:
= Standard Price × (Standard Quantity - Actual Quantity)
= $18 per pound × (610 pounds - 650 pounds)
= $18 per pound × -40 pounds
= -$720 unfavorable
Simply we take the difference between the standard quantity and the actual quantity and then multiply it by the standard price so that the correct value can come
Took me a bit to understand what this is. I have no business sense at all.
Expected Rate of Return = 30%*5% + 9%*75% - 33% * (100 - 75 -5)%
Expected Rate of Return = 0.015 + 0.0675 - 33%*20%
Expected Rate of Return = 0.015 + 0.0675 - 0.066
Expected Rate of Return = 0.0165
This then is expressed as a %
0.0165 = 1.65 % Sounds like you are buying a US short term treasury.
If anyone else answers, take their answer.
Answer:
The BCWS is also known as Planned Value (PV).
So, in this way, <em>PV = 3.125.000</em>
Explanation:
With the data we can obtain the PV as follows:
First, let's calculate EV as EV = CV + AC.
EV = -500.000 + 4.000.000 = <em>3.500.000</em>
After this, we can calculate PV with this formula: SPI = EV/PV
PV = EV/SPI
PV = 3.500.000/1.12 = <em>3.125.000</em>
<em />
<em>We can conclude, with these results, that the project actually is forward about the schedule but with an overcost about the budget. In other words, the project advance must be 41% but now is on 36% due to the negative variance on the costs (CV).</em>
<em />
Answer:
$80
Explanation:
Magda's miscellaneous itemized deductions include the initiation fee for membership in the teachers' union and the dues to the teachers' union. The voluntary fund contribution is not deductible.
All miscellaneous deductions can be deducted as long as they exceed the 2% of AGI threshold, which in this case = $10,000 x 2% = $200
Total itemized deductions = $100 + $180 = $280 - 2% of AGI ($200) = $80