EV
<h3>Earned Value (EV): What is it?</h3>
Value Acquired. EV measures the "value" of the job completed so far. In other words, EV explains the project's accomplishments in concrete terms. EV can be expressed in a Cumulative and Current manner, just as PV and AC. The budget for all of the activities that have been completed to date makes up cumulative EV.
<h3>What is EVM Earned Value Management?</h3>
Earned Value Management (EVM) is a project management technique for monitoring project performance and progress in an objective manner. Scope, schedule, and cost measurements can all be included in a single integrated system when using EVM. It is famous for its capacity to offer precise predictions of issues with project performance.
Learn more about earned value management (evm):
brainly.com/question/4682301
#SPJ4
Answer:
mechanic's lien.
Explanation:
The answer is mechanic's lien.
Mechanic's lien is the creditor protection that the solar contractor encumber the building to ensure the payment
Mechanic's lien is a term given to those security money deposited in the name of the property for the benefit of the people who have invested in the property in terms of labor or materials etc.
Thus when Jane's company refuse to pay the contractor who have installed the solar panels on the roof of the building, the contractor can ensure the payment from Jane's company by claiming it as mechanic's lien.
Thus the answer is mechanic's lien.
Answer:
so far it's going good how about yours?
the first one and third one sis