PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
x = - 5, x = 4
Step-by-step explanation:
Given
f(x) = x² + x - 20
To find the zeros equate f(x) to zero, that is
x² + x - 20 = 0
Consider the factors of the constant term ( - 20) which sum to give the coefficient of the x- term ( + 1)
The factors are + 5 and - 4, since
5 × - 4 = - 20 and + 5 - 4 = + 1, hence
(x + 5)x - 4) = 0 ← in factored form
Equate each factor to zero and solve for x
x + 5 = 0 ⇒ x = - 5
x - 4 = 0 ⇒ x = 4
Triangle
1+1+5=7
7×4=28
28÷2=12
rectangle
12×5=60
whole shape
60+12=72in squared
Part A: Let x and y be the number of persons attending the two-day conference and y be the number of vouchers released. The equation that would best express the given is,
y = 4x
Part B: The number of people attending the conference is determined by dividing the given number of vouchers by 4. The answer is 956.
Answer:
1. 53
2. 20
3. 37
4. 29
Step-by-step explanation:
Since your trying to find the hypotenuse you equation is...
1. 28^2 + 45^2 = C^2
784 + 2025 = C^2
Square Root 2809= C^2
C=53
So after you square root 2809 you get 53.
2. 12^2 + 16^2 = C^2
144 + 256 = C^2
Square Root 400 = C^2
C=20
So after you square root 400 you get 40.
3. 12^2 + 35^2 = C^2
144 + 1225 = C^2
Square Root 1369 = C^2
C=37
So after you square root 1359 you get 37.
4. 20^2 + 21^2 = C^2
400 + 441 = C^2
Square root 841 = C^2
C=20
So after you square root 841 you get 29.