Answer:
see below
Step-by-step explanation:
The angle where chords cross is the average of the intercepted arcs. Here, that is ...
(37° +46°)/2 = (83°)/2 = 41.5°
Angle SUT is 41.5°.
_____
<em>Comment on the error</em>
The measure of an arc cannot be arbitrarily said to be the same as the angle where the chords cross. It will be the same if (a) the chords cross at the circle center, or (b) the opposite intercepted arc has the same measure. Neither of these conditions hold here.
Answer:
The coordinates of H′ are (-2,0).
Step-by-step explanation:
It is given that square EFGH stretches vertically by a factor of 2.5 with respect to the x-axis to create rectangle E′F′G′H′.
If a figure stretches vertically by a factor of 2.5 with respect to the x-axis, then the x-coordinates remains same and the points which lie on the axis are also remains the same after stretch.
It is given that the coordinates of H are (-2,0). This point lie on the x-axis, therefore it will remains the same after stretch.
Therefore the coordinates of H′ are (-2,0).
Miss girl i lost 5 brain cells looking at that
Answer:
The risk consequence of both activities is 1.6 months.
Step-by-step explanation:
We can define a randome variable D: total delay time for the project, and calculate its expected value.
This would be the risk consequence of both activities.
The expected delay time for the project is the sum of the expected delay for task A plus the expected delay for task B. It is assumed the likelihood of a problem in any task is independent of the other.
Then, each expected delay for a task is equal to the probability of a problem multiplied by the consequence (delay time).

The risk consequence of both activities is 1.6 months.