vladimir2022 [97]
3 years ago
11

Divide. Simplify your answer as much as possible.

Mathematics
1 answer:
Reil [10]3 years ago
4 0

Step-by-step explanation:

kkkkkkkkkkkkkkkkkkk. k

You might be interested in
The regular price of a watch is 28.25 during a sale the watch was marked 12% off what was the price of the watch during the sale
goldfiish [28.3K]

we have given that cost price of a watch is $28.25.

it is having an discount of 12%.

discount=discount% /100*(cost price)

discount=12/100*28.25=3.39

sale price=cost price - discount=28.25-3.39=24.86.

the sale price is$24.86

8 0
4 years ago
A garden that is 5ft by 6ft has a walkway 2 ft wide around it. Determine the values of x and y and find the amount of fencing ne
Rudik [331]

Answer:

you will need 30 ft of fencing to determine this

Step-by-step explanation:

so all you need to do is just multiply 6 and 5 then you get 30 hoped this helped bro

8 0
4 years ago
Read 2 more answers
M5_A3. The expected project completion time for the construction of a pressure vessel is 18 monthsand the project variance is 7.
snow_tiger [21]

Answer:

a) 0.3520

b) 0.9884

c) 0.1292

d) 0.1292

e) 0.7648

Step-by-step explanation:

Problems of normally distributed samples can be solved using the z-score formula.

In a set with mean \mu and standard deviation \sigma, the zscore of a measure X is given by

Z = \frac{X - \mu}{\sigma}

After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X.

In this problem, we have that:

The expected project completion time for the construction of a pressure vessel is 18 months. So \mu = 18.

And the project variance is 7. The standard deviation is the square root of the variance, so \sigma = \sqrt{7}.

a) What is the probability that the project will require at least 19 months?

The pvalue of the zscore of X = 19 is the probability that the project will require less than 19 months. So the probability that the project will require at least 19 months is the subtraction of 1 by this pvalue.

Z = \frac{X - \mu}{\sigma}

Z = \frac{19 - 18}{\sqrt{7}}

Z = 0.38

The pvalue of Z = 0.38 is 0.6480.

So the probability that the project will require at least 19 months is 1 - 0.6480 = 0.3520.

b) What is the probability that the project will be completed within 24 months?

This is the pvalue of the zscore of X = 24.

Z = \frac{X - \mu}{\sigma}

Z = \frac{24 - 18}{\sqrt{7}}

Z = 2.27

The pvalue of Z = 2.27 is .9884. This means that the probability that the project will be completed within 24 months is .9884.

c) What is the probability that the project will require at least 21 months?

Same logic as a). We find the pvalue of the zscore of X = 21, then we subtract 1 by this value.

Z = \frac{X - \mu}{\sigma}

Z = \frac{21 - 18}{\sqrt{7}}

Z = 1.13

The pvalue of Z = 1.13 is 0.8708.

So the probability that the project will require at least 21 months is 1 - 0.8708 = 0.1292.

d) What is the probability that the project will be completed within 15 months?

Same logic as b). This is the pvalue of the zscore of X = 15.

Z = \frac{X - \mu}{\sigma}

Z = \frac{15 - 18}{\sqrt{7}}

Z = -1.13

The pvalue of Z = -1.13 is .1292. This means that the probability that the project will be completed within 15 months is .1292.

e) What is the probability that the project will take between 16 and 24 months to complete?

This is the pvalue of Z = 24 subtract by the pvalue of Z = 16.

In b), we found that the pvalue of Z = 24 is .9884

Now we find the pvalue of Z = 16

Z = \frac{X - \mu}{\sigma}

Z = \frac{16 - 18}{\sqrt{7}}

Z = -0.76

The pvalue of Z = -0.76 is 0.2236

So the probability that the project will take between 16 and 24 months to complete is 0.9884 - 0.2236 = 0.7648

8 0
4 years ago
In a 30°-60°-90° triangle, the length of the hypotenuse is 30. Find the length of the longer leg.
Assoli18 [71]
<span>In a 30-60-90  triangle the side opposite the 30 degree angle is half the length of the hypotenuse. 
The shorter leg is </span>the side opposite the 30 degree angle, therefore
the shorter leg = 30/2 = 15

<span>By the Pythagorean theorem
</span><span>the longer leg = </span>√(30² - 15²) = √(900-225) = √675 = 15√3 ≈ 25.98 units
6 0
4 years ago
Anton took out a 20-year loan for $90,000 at an APR of 10.5% compounded monthly, approximately what would be the total cost of h
snow_lady [41]
The answer would be $159,661.69. i think
5 0
3 years ago
Read 2 more answers
Other questions:
  • Find the height of a square pyramid that has a volume of 12 cubic feet and a base length of 3 ft
    7·1 answer
  • 1 Point
    12·2 answers
  • Write two addition sentences where the<br> sum is negative
    7·2 answers
  • What is the quotient? 1462 divided 58 Enter your answer as a mixed number in the simplest form
    7·2 answers
  • An expression is shown.
    8·1 answer
  • I need help asap please help!!
    7·1 answer
  • Which function has a maximum with the same maximum value as
    10·1 answer
  • 3×(3+12÷3)−4 Can someone please answer this?
    5·1 answer
  • What is 300 to the nearest ten
    15·2 answers
  • What sum is most likely to occur when the two spins are added together
    5·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!