Paladinen [302]
4 years ago
6

M5_A3. The expected project completion time for the construction of a pressure vessel is 18 monthsand the project variance is 7.

(Note: when using the Z tables – round your Z values to two decimal placesbefore getting the probabilities from the tables. DO NOT round standard deviations prior to calculating Zvalues)NOTE: Enter probabilities as decimals (i.e 92.31% should be entered as 0.9231)a) What is the probability that the project will require at least 19 months? (Enter 4 decimal placesfrom distribution tables)b) What is the probability that the project will be completed within 24 months? (Enter 4 decimalplaces from distribution tables)c) What is the probability that the project will require at least 21 months? (Enter 4 decimal placesfrom distribution tables)d) What is the probability that the project will be completed within 15 months? (Enter 4 decimalplaces from distribution tables)e) What is the probability that the project will take between 16 and 24 months to complete? (Enter4 decimal places from distribution tablesShow Work
Mathematics
1 answer:
snow_tiger [21]4 years ago
8 0

Answer:

a) 0.3520

b) 0.9884

c) 0.1292

d) 0.1292

e) 0.7648

Step-by-step explanation:

Problems of normally distributed samples can be solved using the z-score formula.

In a set with mean \mu and standard deviation \sigma, the zscore of a measure X is given by

Z = \frac{X - \mu}{\sigma}

After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X.

In this problem, we have that:

The expected project completion time for the construction of a pressure vessel is 18 months. So \mu = 18.

And the project variance is 7. The standard deviation is the square root of the variance, so \sigma = \sqrt{7}.

a) What is the probability that the project will require at least 19 months?

The pvalue of the zscore of X = 19 is the probability that the project will require less than 19 months. So the probability that the project will require at least 19 months is the subtraction of 1 by this pvalue.

Z = \frac{X - \mu}{\sigma}

Z = \frac{19 - 18}{\sqrt{7}}

Z = 0.38

The pvalue of Z = 0.38 is 0.6480.

So the probability that the project will require at least 19 months is 1 - 0.6480 = 0.3520.

b) What is the probability that the project will be completed within 24 months?

This is the pvalue of the zscore of X = 24.

Z = \frac{X - \mu}{\sigma}

Z = \frac{24 - 18}{\sqrt{7}}

Z = 2.27

The pvalue of Z = 2.27 is .9884. This means that the probability that the project will be completed within 24 months is .9884.

c) What is the probability that the project will require at least 21 months?

Same logic as a). We find the pvalue of the zscore of X = 21, then we subtract 1 by this value.

Z = \frac{X - \mu}{\sigma}

Z = \frac{21 - 18}{\sqrt{7}}

Z = 1.13

The pvalue of Z = 1.13 is 0.8708.

So the probability that the project will require at least 21 months is 1 - 0.8708 = 0.1292.

d) What is the probability that the project will be completed within 15 months?

Same logic as b). This is the pvalue of the zscore of X = 15.

Z = \frac{X - \mu}{\sigma}

Z = \frac{15 - 18}{\sqrt{7}}

Z = -1.13

The pvalue of Z = -1.13 is .1292. This means that the probability that the project will be completed within 15 months is .1292.

e) What is the probability that the project will take between 16 and 24 months to complete?

This is the pvalue of Z = 24 subtract by the pvalue of Z = 16.

In b), we found that the pvalue of Z = 24 is .9884

Now we find the pvalue of Z = 16

Z = \frac{X - \mu}{\sigma}

Z = \frac{16 - 18}{\sqrt{7}}

Z = -0.76

The pvalue of Z = -0.76 is 0.2236

So the probability that the project will take between 16 and 24 months to complete is 0.9884 - 0.2236 = 0.7648

You might be interested in
the sum of nakias and tchallas age is 41 years. five years from now, the sum of their ages will be three times nakia's present a
Tresset [83]

Step-by-step explanation:

Nadia's is 41 years old.

8 0
3 years ago
X + 8 = -7 help me our only got 5 more minutes !
Nastasia [14]

x + 8 = -7

move +8 to the other side

sign changes from +8 to -8

x+8-8= -7-8

x=-7-8

Answer:

x= -15

7 0
3 years ago
Read 2 more answers
drew bought a chemistry book for $30. later that book was marked down by 20%. what was the cost of the book with the discount?
drek231 [11]

Answer:

It would be 6 dollars

Step-by-step explanation:

20 percent of 30 dollars is 6 dollars.

If an item costs 30 dollars and it's on sale for 20 percent off, how much will you save? To figure this out, you need to find 20 percent of 30.

This is easy to do in your head. Think of what 10 percent would be. 10 percent of 30 would be the same as .10 x 30, or 3. So, 10 percent off is 3 dollars off.

20 percent is twice as much as 10 percent. If 10 percent off is 3 dollars, then 20 percent off would be 2 x 3 or 6.

20 percent of 30 dollars would be 6 dollars.

3 0
3 years ago
Every 1 have a great day. If sum 1 pull you down get back up<br><br><br> Have a good day
dmitriy555 [2]

Answer:

I hope you have a great day too

4 0
3 years ago
Find the perimeter and the area of the polygon with the given vertices. W (11,2), X (11,8), Y (14,8), Z (14,2)
liberstina [14]

Answer:

The perimeter of the polygon = 18 units

The area of the polygon will be A=18 square units

Step-by-step explanation:

<u><em>Computing the Perimeter of the Polygon: </em></u>

Considering the polygon with vertices

  • W (11,2)
  • X (11,8)
  • Y (14,8)
  • Z (14,2)

As the polygon is drawn in coordinate plane as shown in figure a.

From the attached figure a, we can observe that

  • The length of the side WZ = 3 units
  • The length of the side ZY = 6 units
  • The length of the side WX = 6 units
  • The length of the side XY = 3 units

So, the perimeter of the polygon can be calculated by taking the sum of the lengths of all sides i.e.

The perimeter of the polygon = WZ + ZY + WX + XY

                                                  = 3 + 6 + 6 + 3

                                                  = 18 units

<u><em>Computing the Area of the Polygon: </em></u>

Area can be calculated by multiplying the length and width of the polygon.

A=lw

So, the area will be:

A=lw

A=(3)(6)

A=18

Therefore, the area of the polygon will be A=18 square units

Keywords: area, perimeter, polygon

Learn more about area and perimeter from brainly.com/question/2328840

#learnwithBrainly

5 0
3 years ago
Other questions:
  • Scott and Teri read mystery novels. Teri has read 3 less than 5 times as many as Scott. She has read 17. How many has Scott read
    11·2 answers
  • Carrie took a 24-hour train ride from Colorado to Illinois. If she arrived in Illinois at 2:45pm CST on Wednesday, when she did
    13·1 answer
  • Write (5x)2 without exponents.
    5·2 answers
  • The lock is numbered from 0 to 49. Each combination uses three numbers in a right, left, right pattern. Find the total number of
    5·1 answer
  • A cylinder is inscribed in a right circular cone of height \displaystyle 9 inches and radius (at the base) equal to \displaystyl
    14·1 answer
  • Simplify
    7·1 answer
  • Find the measure of the indicated angle to the nearest degree.
    11·1 answer
  • Find mZGJH for regular octagon ABCDEFGH
    15·1 answer
  • two angles join to form a straight line the first angle measures 100 degrees what is the measure of the second angle​
    8·1 answer
  • If a garden hose can fill up a 5 gallon
    15·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!