Answer: The required probability is 0.82.
Step-by-step explanation:
Since we have given that
Number of projects = 3
So, probability of getting each project = 
Probability of first path being completed in 43 days = 0.7
Probability of second path being completed in 43 days = 0.85
Probability of third path being completed in 43 days = 0.90
So, Probability that the project will be completed on time would be

Hence, the required probability is 0.82.