From the critical path that's given, the total crashing cost will be $530.
<h3>What is a critical path?</h3>
A critical path simply means the longest sequence of tasks that one will have to complete in order to complete a project.
In this case, from the information given, the critical path will be:
= 0 + $130 + $400
= $530
In conclusion, the correct option will be $530.
Learn more about critical path on:
brainly.com/question/10693558
Answer:
A)$135,000
Explanation:
service fee 250
average wage 175
contribution 75 this is the ammount generate per hour billed
expected hours billed for the year 10,000
hours x contribution per hour = total contribution
10,000 x 75 = 750,000
Operating cost <u> (615,000) </u>
Earnings before taxes 135,000
It reduced the cash flow to product innovation. It led to increased operating costs.
Answer:
The correct answer is C. 7.22 percent
Explanation:
To find the arithmetic risk premium for the 5 year period, the formula is
Average risk premium for the period = Sum of risk premium for each year / number of years = ∑ra(i) - rf(i) / n
ra = asset or investment return / 100
rf = risk free return / 100
Where i represents each year.
Sum of risk premium for each year = (0.187 - 0.052) + (0.058 - 0.034) + (0.079 - 0.028) + (0.108 - 0.034) + (0.116 - 0.039) = 0.361
Average risk premium = 0.361 / 5 = 0.0722 = 7.22 / 100 = 7.22 percent