Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Answer:
b. 6
Step-by-step explanation:
I'm not 100% sure if this is the answer but here was my thinking process:
1/4 of 24 is 6, and 6 + 3 is 9, so the brothers age is probably 9, and then 24-9 is 15, and the difference between 15 and 9 is 6. Once again I don't know if this is right or not, but either way I hope this helps!
First angle = x
Second angle = x - 42
Sum both complementary angles = 90
x+x-42=90
2x=132
x=66⁰ - First angle
x-42=66-42=24
24⁰ - Second angle