THE PROGRAM MANAGER will approve the realignment. The program manager is able to approve this realignment because a reprogramming action is not required. If a reprogramming action is required, that meas the change will be substantial, in this case the program manager will not be qualified to approve the realignment.
Answer:
$ 2,500 as far as i know.
Explanation:
Answer and Explanation:
The journal entries are shown below:
1. Cash Dr $1,000,000
To Bond payable $1,000,000
(Being the issuance of the bond is recorded)
For recording this we debited the cash as it increased the assets and credited the bond payable as it also increased the liabilities
2. Interest Expense Dr ($1,000,000 × 5% × 1 ÷ 2) $25,000
To Cash $25,000
(Being the interest expense is recorded)
For recording this we debited the interest expense as it increased the expense and credited the cash as it decreased the asset
Answer:
Confirm that all the stakeholders have had input into the scope.
Explanation:
When assigned to a new project, the project manager may be tempted to start planning immediately. One may conclude that the first thing is planning. It will be wise and smart to understand the project charter before planning. Therefore, it is very important to " Confirm that all the stakeholders have had input into the scope." So, Option B is the correct answer.
Answer:
$530,672
Explanation:
Base on the scenario been described in the question, we can use the following method to compute the avoidable interest on this project
Use the attached file below to find the solution to given problem .