Answer:
C. $3,400 F
Explanation:
The computation of the direct labor rate variance is shown below:
Direct Labor Rate Variance
= (Standard rate - Actual rate) × Actual hours
= ($12 - $200,600 ÷ 17,000 labor hours) × 17,000 direct labor hours
= ($12 - $11.8) × 17,000 direct labor hours
= $3,400 favorable
Since standard cost is more than the actual cost which leads to favorable balance
Answer:
C) Credit card companies want to increase profits by promoting slower repayment, and actual customer repayments will be anchored by the smaller payment options
Explanation:
It is always a bad idea to only pay the minimum monthly payment on a credit card debt, since the APR charged is much higher than other personal loans. If someone only makes the minimum payment and continues to purchase goods or pay services, their balance will continue to grow.
Answer: 10/40/40/10
Explanation:
Under the 10/40/40/10 rule, 10% of the employees tend to follow ones own attitudes and values, i.e. they believe that their beliefs are more remarkable than those around them. 40% of the employees try to go along with the organization policies. The other 40% might follow their assigned work group whereas the last 10% tend to take advantage of such circumstances just in case if degree of penalization is lower to that of the benefit and also risk of getting caught is less.
Answer:
$33.44
Explanation:
The computation of the intrinsic value of the share is shown below:
= Next year dividend ÷ (Required rate of return - growth rate)
where,
Next year dividend is
= $2.16 + $2.16 × 4.50%
= $2.16 + $0.0972
= $2.2572
The required rate of return is 11.25%
And, the growth rate is 4.50%
So, the intrinsic value is
= ($2.2572) ÷ (11.25% - 4.50)
= $33.44
Answer: c. 78,000 equivalent units.
Explanation:
Equivalent units for conversion is calculated as:
= Units completed and transferred out + Equivalent ending work in process
Units completed and transferred out:
= Units started into production - Ending units
= 90,000 - 20,000
= 70,000 units
Equivalent ending work in process = 40% * 20,000 work in process units
= 8,000 units
Equivalent units for conversion = 70,000 + 8,000
= 78,000 units